|
Engineering Term Paper - Construction
Dewatering Engineering
Click Here To View Top Term Papers Sites
Planning and authorization
The old wastewater treatment plant Duisburg - Kaßlerfeld that was built in
1954 had a mechanical - chemical stage of treatment consisting of screen,
grit removal and settling tanks as well as a digester and a sludge deposit.
Already in the early 1970s first plans were made for a mechanical -
biological plant that could not be realised for several reasons. The plans
included a sludge incineration plant, which got no approval since the air
immission load was then already higher than allowed.
The new plan, which was submitted in 1982, contained a concept of biological
purification that was designed for the breaking up of carbon. The biological
treatment had to be altered in the cause of the process of approval of the
concept in such a way that a nitrification of ammonia also became possible.
By the act of approval of concept the plan to renew the wastewater treatment
plant Duisburg-Kaßlerfeld was authorized on 1. September 1987.
The part of the plan concerning wastewater technology was revised after the
authorization in order to allow a specific nitrification and denitrification
as well as the elimination of phosphate. The revisions were included in the
authorization by an alteration of the approval of concept in summer 1989.
Due to its importance for the infrastructural development in the catchment
area the realization of the wastewater treatment plant Duisburg-Kaßlerfeld
was subsidised by the federal government of Northrhine-Westphalia with a
subvention covering up to 80 % of the costs of investment.
Click Here To View Top Term Papers Sites
Structural engineering and project management
The construction works started late in 1988. In summer 1992 the carcase work
was completed. As a first measure the entire area was surrounded with a
tightening wall in order to protect it against ground water floods. This
wall is 60 cm thick, 1,450 m long and has a surface of about 36,000 m2. It
reaches down to a maximal depth of 45 m in the underground. This complex
construction was necessary because it was decided to avoid an intake pumping
station for economical reasons. Thus, the wastewater treatment tanks lie
below the level of the rest of the area.
The construction work was considerably influenced by the request to maintain
the previous degree of wastewater treatment and the discharge of the
wastewater during the entire time of construction. Due to the construction
plans and the necessity to protect certain plants, which were already, or
still in operation the construction work faced severe obligations.
Additionally considerable masses had to be moved. In the allotment of the
wastewater treatment plant alone about 500,000 m3 of soil had to be moved
and about 52,000 m3 concrete had to be produced with 6,000 t of steel and
100,000 m3 of sheating.
The facts that all parts of the plant could be started up in time and that
the estimated costs were not exceeded prove together with the now existing
operating results the success of the project management and the quality of
the means of control and supervision used.
Click Here To View Top Term Papers Sites
Wastewater treatment processes
The wastewater is treated mechanically, biologically and chemically. The
mechanical treatment uses a screening plant, an anaerated grit removal tank
and primary settling tanks. The wastewater runs through the screening plant
in four parallel flows with a backraking coarse screen (60 mm clearance) and
a fine screen (20 mm clearance) each. The screenings are dewatered and
transported via converter belts to containers. The entire plant was erected
in a closed building for reasons of possible emissions and in order to
guarantee an undisturbed operation even during winter.
After flowing through the grit channels the wastewater enters the primary
settling tanks. Due to the fact that alterations had to be made for
nitrification, denitrification and phosphate elimination the total volume of
the four primary tanks was reduced to 5,200 m3. This reduction effects a
coarse sludge removal in only 0.6 hours.
The separation of the aerated sludge from the treated wastewater takes place
in the final clarification for which there are five rectangular tanks. These
final clarification tanks have a total volume of 40,000 m3. Two sludge
scrapers each remove the sedimented sludge. Due to the fact that the primary
tanks are very small the waste activated sludge is thickened seperately. The
treated wastewater is discharged through perforated pipes.
The chemical treatment eliminates the phosphorous, which together with
nitrogen can cause an undesired mass development of algae in the receiving
waters.
Click Here To View Top Term Papers Sites
Operation and control
All information relevant for the operation and control of the plant are
transmitted to the operation center. Here the information is processed with
the help of a computer and thus provides the necessary data for the staff.
With the help of colour screens the shift-leader gains detailed insight into
the conditions of any part of the plant and can take the relevant measures
in case of disturbances. A total control of the plant is guaranteed by a
large mosaic plate which shows the entire plant and which immediately
signals disturbances. Apart from the operation center there are several
sub-centers where the power station, the dewatering of sludge, the sludge
digestion and the sludge thickening are controlled.
In order to operate and control the plant according to the relevant
standards and to optimise the costs of energy consumption complex plants for
process control were installed. The process control is of special
significance for the operation of the biological treatment.
Influx and discharge of the wastewater treatment plant as well as the
internal wastewater and sludge flow are not only controlled by the local
analytical instruments which are continuously working but, more important,
by the laboratory of the wastewater treatment plant and the central
laboratory of the Ruhrverband in Essen. The operational data are registered
in reports and can be plotted as diagrams.
Click Here To View Top Term Papers Sites
Sludge treatment processes
The Sludge treatment processes consist of the unaerobic stabilization of
sludge by digestion and the mechanical dewatering of sludge. This plant was
started up in spring 1991.
The main part of the sludge stabilization plant consists of three digesters
with a volume of 8,720 m3, each which are operated, in parallel as
mesophilic reactors at a temperature of 35 to 38 oC. The organic substances
of the sludge are decomposed in the digesters to such an extent that the
sludge can be dewatered afterwards and disposed without the emission of
odor. The sludge remains in the digesters for about 21 days. The digestion
process produces about 10,000 m3 of gas per day, which is stored in two gas
tanks with a volume of 4,000 m3 each and then used for the generation of
energy and compressed air in gas motors. The waste heat is used in turn for
providing the digestion tanks with the temperature needed. Additionally, the
buildings of the wastewater treatment plant are heated with this waste heat.
Whereas the primary sludge can be pumped directly from the primary
clarifiers to the digesters the waste activated sludge from the secondary
tanks has to undergo a preliminary thickening. This can be affected
statically in gravity thickeners as well as mechanically by centrifuges.
Both processes can be operated either in series or in parallel.
The digested sludge is dewatered in three chamber filter presses with a
volume of 14m3 each. In order to improve the conditions of dewatering the
digested sludge is conditioned by adding slaked lime and ferric chloride.
Additionally it is statically thickened in a reaction thickener for 24
hours. With the help of high-pressure pumps the conditioned sludge is pumped
to the chamber filter presses. By dewatering the digested sludge is
concentrated to 40% of dry solids. This means a reduction of volume of about
90%. The supernatant and the filtrate, which are thus obtained, are led to
the influx of the wastewater treatment plant. After the pressing the chamber
filter presses are opened and the dewatered sludge falls into the silos
situated underneath the presses. From there lorries carry the dewatered
sludge to the mono-deposit on the Ruhrinsel Raffelberg about seven
kilometers away. (ruhrverband.de)
Click Here To View Top Term Papers Sites
Sludge Dewatering Equipment
When industrial or municipal wastewater is treated through settling or
flotation, its liquids and solids are separated. The water is discharged,
leaving the concentrated solids behind. Many types of equipment are
available for sludge dewatering, including belt filter presses, sludge
dryers, vacuum filters, centrifuges, screw presses, plate and frame presses
and drying beds. The type of sludge generally determines the type of
equipment required. Treatment chemicals often are used in conjunction with
sludge dewatering equipment to improve solids capture and enhance equipment
performance. Numerous choices are available today, from single dewatering
components to complete customized dewatering systems. In many cases, PLC
instrumentation also makes possible the control of an entire dewatering
system from one location. (pollutionengineering.com
Project Scope
Selection of the proper equipment and compatibility with the existing
processes is key to an effective dewatering program. The following is a
brief discussion of the work tasks involved in addressing these key issues
as well as others. There are a number of dewatering options, which can
provide the solids concentration desired for dewatered biosolids storage and
land application. However, of these options the belt filter press and the
centrifuge are generally the most common and cost effective for the size of
Sandy’s process. These two processes have little in common except for being
capable of dewatering wastewater sludge. The technology, size of equipment,
power consumption, chemical usage and end product all differ between the two
processes.
Click Here To View Top Term Papers Sites
The existing solids handling facilities will need to be evaluated to
determine their compatibility with the proposed process. Currently, the City
uses a lime slurry system to raise the pH of the liquid sludge in order to
stabilize it for land application. Maintaining this system would result in
processing a lime-stabilized sludge through the dewatering equipment. There
are concerns with using this lime system with any dewatering equipment
options due to the abrasive characteristics of the lime slurry and the
potential for it to foul equipment.
With the dewatering process, water is removed from the biosolids and
reintroduced back into the plant’s waste stream. This filtrate is relatively
high strength wastewater and, at the volumes released from the equipment
during operation, it has the potential to upset the treatment process.
Provisions may be necessary to convert a cell in the existing WASH tank to
hold the filtrate and release it slowly back into the waste stream, similar
to the existing decant process. With a dewatered biosolid, the process of
transporting and storing biosolids on site will dramatically change. Once
the sludge is dewatered, its characteristics are similar to soil. Conveyers
and loaders are necessary to move the material and it will require covered
storage areas so it can be piled and kept dry until it is applied to the
land. In addition, transportation and land application equipment will need
to be acquired to properly land apply the material. (ci.sandy.or.us)
Backflow prevention
A backflow preventor is a mechanical device used to prevent foreign
materials from entering and contaminating the drinking water supply. Plant
Engineering performs, in conjunction with the City of Newport News, an
annual backflow prevention device inspection and test of all connections to
buildings and water main supplies. Each device is tested to demon. Potable
water is processed through a filtration system to remove ions for the LCW
system. The Plant Engineering maintains the LCW and ICW systems Department.
The systems provide a continuous source of LCW for cooling accelerator
support systems during accelerator operations, as well as other water-cooled
equipment. The ICW system, which removes heat from the LCW for the end
station beam energy dissipaters, contains corrosion inhibitors to protect
the piping and heat exchanger surfaces. The CW system removes heat from the
ICW system or the LCW system in all areas except the end station beam energy
dissipaters. The CW is processed and the heat is discharged to the air
through evaporation.
Click Here To View Top Term Papers Sites
Fire suppression water
The potable water system provides the source for all built-in Jefferson Lab
fire extinguishing systems. The Plant Engineering Department manages this
system. Plant Engineering's Maintenance Management Program ensures that
fire-fighting water pressures are adequate and that sprinkler systems are
operable.
Cooling tower water
Cooling towers remove/reject unwanted heat from air conditioning, cryogenic,
and other systems. Potable water for use in cooling towers is treated to
prevent corrosion and inhibit bacterial growth. Note that once water is
introduced as make-up water in the tower basin, it is no longer potable.
Plant Engineering manages this program to support facility usage.
Implementation of the Maintenance Management Program ensures cooling tower
water quality.
Activated Water Management Program
Water that accumulates within the tunnels, beam energy dissipaters, and
experimental halls may become radioactive as a result of high-energy photons
and neutrons interacting with stable oxygen, deuterium, and impurity atoms
in water. The Activated Water Management program provides containment for
potentially contaminated water from any discharge so that it can be sampled
and the total activity counted prior to being discharged. Water that is
detected at levels above background values for radioactivity must be
disposed of through the sanitary sewer distribution system or by other
approved means. Water that is at or below background levels may be
discharged to the surface water runoff system. (jlab.org)
Click Here To View Top Term Papers Sites |